There's hope that the trade dispute with the U.S. will not affect the budget or timeline as construction progresses at Blue Coast District School in Forest.
The Kindergarten to Grade 12 school will be built on Townsend Line, near The Shores Recreation Centre.
Lambton Kent District School Board (LKDSB) Associate Director of Corporate Services Brian McKay said site preparation work took place over the summer months.
"Then we started in September with the foundation," he said. "The weather in the fall has really been a help to us from a construction standpoint and making good progress on the foundation work, including the footings."
McKay said the building outline started with the secondary side and shared spaces, before moving toward the elementary side.
The building is expected to start taking shape in the new year.
"Putting up the steel frame, the steel structure of the building should start in January," McKay said. "Weather appropriate, once steel starts to go up, the building really starts to quickly take shape and look like a building."
Currently, the project is proceeding on budget and within target of the LKDSB's timeline for the projected September 2028 school opening.
Wellington Builders was awarded the $74 million contract in May 2026, roughly seven months after a ceremonial groundbreaking took place.
McKay said the tender process was done twice because it initially came back over budget. He also said the school board has been working closely with the contractor to understand material pricing and if tariffs will apply.
"We've only had one instance where there's been a direct tariff impact at this time that we've been made aware of, but it was a fairly small dollar amount so it wouldn't have any change to the overall price," he said. "So we're hopeful we'll continue to have good luck with our pricing."
McKay also said working with great contractors and subcontractors, eager to build in the community, has helped throughout this process.