Armow Wind Turbine Construction Underway

Work is underway on a major turbine project north of Kincardine.

A construction update from Armow Wind says access road construction began in early March and substation excavation began in mid-March.

6 km of access roads have been completed. There are plans for another 40 km.

Five of the 91 turbine foundations have been excavated, and three concrete foundations have been poured.

Turbine deliveries should begin by mid-May. The turbine blades are being made in Tillsonburg and the turbine towers are being made in Windsor.

Read More Local Stories

File photo courtesy of  © Can Stock Photo Inc. / dehooks

Scoreboard, August 1

The Jays opened their home series against the Cardinals with a win off another Dylan Cease gem.

Grand Bend Beach June 25, 2020 Image courtesy of Grand Bend Pier Beach Cam.

Youth volunteers practice coastal conservation

Nine young volunteers aged 11 to 17 spent three days exploring and protecting the Lake Huron coastline during the Coastal Conservation Youth Corps' inaugural program in Grand Bend from July 21 to 23.